On Tuesday, September 29th, Kevin from Cheyenne Wind was out and did the test run prior to final inspections of our generator. How wonderful to finally see it spinning. We were issued our serial number, computer USB antenna, and SkyView 2.o software CD. This software allows us to know exactly what our generator is doing at any point in time. It is now installed on the computer and we have done our own “test run” of the generator. I am sure that we will be enthralled with the software for some time to come.
So there are three inspections that must occur. The building permit final inspection should be today. Next, the electrical permit inspection will be performed. Finally, Mountain View Electric Association will do a final inspection and switch out our analog meter with the digital net meter. At that time, the Matrix generator will be fully functional.
New facts regarding it operation were learned yesterday as well.
At 56 mph wind speed, the generator will lock itself and turn off. It will wait one hour before trying to restart and test the wind speeds to determine if it can safely operate. This is done to avoid damage to the generator.
The generator does NOT provide power in the absence of grid power. If we have a power flicker, the generator will shut down and will try to resume every 10 minutes. In the event of an extended power outage, this will continue until power resumes. If we had a backup generator wired into our home, we could shut the connection to the MVEA grid, the wind generator would sense the backup generator’s function and begin producing power to assist production in that closed environment. We may have to look in to that.
Stay tuned!
==End of Chapter==